Lawley NG6, No. 233

Update from Lukas Nel – 30 July 2012

We beat all the tube ends in the firebox and intend to start the hydraulic testing of the boiler on 2nd August. We set one week aside to complete the hydraulic testing of the boiler. We still need to replace the smoke box front of the locomotive boiler and fit the smoke box door before we can start repairs to the faulty injectors and the bad slipping of the locomotive.

Below are two photos of the finished product of the beating of the tube ends of the firebox side of the boiler.

sandstone_2012_118

 

sandstone_2012_119

We have completed the steelwork on the Lawley tender. We still do need to do some extensive repairs to the tender frames and draw gear.

Below are some photos of the plate work done to the tender.

sandstone_2012_120

sandstone_2012_121

Update - 30th July 2012

The Bloemfontein workshops have completed the riveting of the tender. Due to the heavy workload we are currently looking to expand our labour force at this facility.

sandstone_2012_111

sandstone_2012_112

Expanding tubes firebox end

sandstone_2012_114

sandstone_2012_117

Expanding the smoke box end

Further progress on the repairs of the Lawley and tender is on schedule.

Sandstone_2012_095

Bottom half of tender renewed. Rivet holes to be drilled and tank to rivet.

sandstone_2012_106

Diesel fire use to anneal the Lawley locomotive tube ends.

Preparation of the tubes ready for the retube of the Lawley NG6 no 233 boiler are underway.

sandstone_2012_103

Diesel burner.

sandstone_2012_108

Annealed boiler tubes ready to use.